Outside stonework

While we enjoy the last of the glorious Indian summer, the guys work outside.  All the pointing has to be dug out and replaced as it's of poor quality and not a good colour - it looks grey against the lovely honey coloured stone.  The two photos at the bottom show it once they've finished raking it out.  Of course, having done this, they now have to re-point it - suspect that'll take a whole lot longer than removing it.








Wednesday, 10 September 2014

Kitchen

They continue to work on the kitchen - it's going to be a good sized room - about 4.5m x 7.5m.  The room has two levels of ceiling as it goes up into the space on which the en-suite bathroom sits (due to the presence of a large, immoveable beam).  The photos below show the higher height and in the first one you can also see where the ceiling level goes up.

I go to see a kitchen made and installed by Mark the carpenter and really like it (phew), so we begin work to finalise the kitchen design which is really exciting.  I show it to a few people who all approve (perhaps they're just being nice) but I'm happy with the layout etc.  Now I need to decide on colour.  The units will be made of tulip wood and painted.  I'm painting lining paper with lots of different colours and this week's favourites are a light taupe and a pale french grey.  It's a dilemma, but thankfully I don't need to decide for a few more weeks.

I'm planning to have a tiled floor with tiles that look like wood flooring and also have to think about the wall tiles - so still lots to do.  I wonder if the Aga, which was ordered last Christmas, will go in before the end of the year - I do hope so





Thursday, 31 July 2014

Planning update

No photos with this entry, but an update on the (lack of) progress with the planning application.  The application went in in the middle of May and since then there has been total silence.  Just before everyone goes on holiday and about 10 weeks after the application we ask for an update.  Unfortunately, the original conservation officer has gone off on long term sick leave and in typical local government style, no-one has picked up his work or thought to let us know.

In mid August, once everyone's back from leave, a new conservation officer is appointed who picks up the file and reviews it.  While this takes time, he is helpful on a number of issues while sticking his heels in on others including those the original conservation officer was unhappy with.  We go back and forward over several weeks and it seems we are making some progress.  There are two sticking issues, but other than that everything else seems to be acceptable.

The two problem areas are the glass box extension and the proposal to remove/raise the beam on the top floor which means the door is about 2 feet 6 high and you have to duck in and out of the room.  The planning consultant is confident we'll win both of these on appeal, but it's going to cost more time and (of course) money.  The appeal process will take at least 14 weeks, so it looks like this work won't be done until 2015.

We wait for the written confirmation, but, disaster - the 3rd planning officer or case worker, rejects the whole application and promptly goes off on holiday.  The planning consultant is not happy (to say the least), and it appears we'll need to wait for another 8 weeks for even those things they were happy with to be approved..........it's horribly frustrating, but it seems little we can do.  Luckily, there's quite a lot they can get on with even without the planning permission.

Wednesday, 16 July 2014

Plastering

The plaster has been working hard and has been doing the final coat in some of the rooms - looks fabulous.  As the house is so old, they have to use original materials and so it's taken a LONG time - way longer than more modern methods.  I guess it's worth it, but given it won't be visible once it's painted it's another one of those invisible projects which run throughout the house - can't wait till we get to to works that will be visible post completion!






Wednesday, 2 July 2014

Bedroom Fireplace

In the first floor bedroom there's a fireplace (now clocked off) with a surround which was painted (badly), so the guys have stripped it off.  I was hoping they'd find the original wood underneath, but sadly it's been stained and so doesn't look that great.  They'll finish stripping the old paint, but I suspect we'll end up painting it over again in due course.  As the fireplace has been blocked off, it won't be used so will have to find something to put there (everyone reading this will be groaning at the thought of me putting clutter there !!)



Friday, 27 June 2014

Bathroom wall

When they start plastering what will be the bathroom on the first floor, the old plaster has to be completely removed leaving this gorgeous stone wall - so I've decided to keep this wall in stone so it will be pointed and sealed in due course.





Friday, 20 June 2014

Use your imagination

This is a lovely sunny south facing spot between the old barn and one of the outbuildings.  The crumbling wall at the back will be built up, some nice paving laid and before you know it I'll have a little sun trap for my morning coffee.........now, just need a kitchen to make it!